Abus,
IPPs and PPAs
The Philippine Star
May 13, 2002
Out with the
Abu Sayyafs. Enough with the American military exercises.
With the Manila
Electric Company (Meralco) billings taking the heat off issues like
the Balikatan and the insurgency problem in Mindanao, Filipinos
have found themselves a new kontrabida. These are the independent
power producers (IPPs).
Only a few years
ago, IPPs were the Filipinos' heroes with promises to save them
from the inconveniences of 12-hour daily brownouts. They were the
saviors of the times and the public just couldn't wait for these
new power plants to bring light to dark homes and energy to run
industries.
Least of the
public's concern was how it was going to be done. Cost also mattered
little. Just do it, the country implored.
IPPs were the
product of the build-operate-transfer (BOT) law passed in 1987 by
the Aquino government. The law encouraged the private sector to
enter the power generation business and assist the government in
funding the country's future power requirements. In effect, with
the BOT law, Napocor's "generation monopoly" was dismantled.
In the early
90s, under President Fidel V. Ramos, the country dreamt of becoming
the fastest growing economy in Asia. The government knew there was
no way such a vision could be achieved without a stable supply of
electricity.
During those
times, the Philippines had not shed off the effect of military coups
and the perception of a weak political leadership. Understandably,
the country was seen as a high economic risk; investors could only
be enticed if they were guaranteed back their capital at a faster
than normal pace, plus plenty of perks on the side.
The scheme for
seducing IPPs in the country, more so on a fast-track basis, was
without doubt generous. Payback time was half shorter than those
of comparable projects in other countries, and investments were
insulated from many risks. The smart power plant investor naturally
grabbed the offer.
Part of the IPP contract provisions is the now famous take-or-pay
clause under a Power Purchase Agreement (PPA). When an IPP agrees
to construct a power plant, it is premised on a projected demand,
usually agreed with government. Demand for electricity is estimated
based on calculations of how the economy would grow. This is usually
based on conservative figures, and backfires are not often expected.
The IPP protects
its investment by asking for a guaranteed sales volume premised
to pay for its capital amortizations, operating costs and profit.
Unfortunately, no one foresaw the Asian financial flu of 1997. As
what happened, demand and consumption dropped, and the anticipated
boom never came.
Now, the IPPs
are no more the darlings they used to be, and they have morphed
into vultures taking advantage of a nation in despair. Regarded
as brilliant financial agreements in the early 90s, IPP contracts
are now viewed as onerous.
If plans had
not gone awry, all of Napocor's other power plants would have been
privatized during the last decade; similarly, the transmission business
would also have been sold. Tough luck that the Asian financial crisis
happened. Overnight, Napocor found itself with the burden of PPAs
in a magnitude it had never imagined.
Next question
is: what should be done?
IPPs, I believe,
are the future of the industry. The current take-or-pay clause of
existing PPAs is definitely a heavy load on Napocor's viability
and the public's sanity. But a solution, no matter how long it will
take to be resolved, is taking shape. The government has the option
of either selling off or buying these contracts. Or IPPs may be
encouraged to aggressively seek other markets aside from that controlled
by Napocor. This could mop up the unused capacity with the end-view
of reducing the stranded cost resulting from under-utilized off-takes.
New IPPs may
provide electricity to islands in a more cost-effective way. Napocor,
at the moment, is a very costly operator because it is burdened
by cross subsidies among island grids. Transmission operations should
also be deregulated. Let the private sector build and operate transmission
lines so that cross-subsidies, pilferages and transmission losses
are better managed.
Given the brouhaha
that IPPs are now experiencing, it may take awhile to bring in new
investors in the power sector under less bighearted terms. New financial
packages though are being developed in other countries, and these
may be applicable to ours. Our technocrats should be able to rise
to this challenge.
It is a perception
that indigenous fuels used by geothermal and hydroelectric power
plants are inexpensive. In truth, both are way over the cost of
imported oil or even coal. Areas where geothermal and hydroelectric
plants operate should be billed the real cost. Or perhaps, the government
should consider mothballing them.
There are alternative
fuels that offer attractive solutions for the country. Solar is
now at a stage where it is economically competitive if used in areas
that do not immediately have the potential of being connected to
a major power plant or transmission grid. Solar is also commercially
viable for street or security perimeter lighting.
Meanwhile, the
witch-hunting is starting. A few weeks from now, the results of
a Malacanang-led review on the IPPs would be completed. Expect a
listing of IPPs that hurt our pockets most. I can almost hear public
crying out for blood.
At this stage,
existing IPPs would be naïve to think that they can hide behind
the legal mumbo-jumbos that bind PPAs. It is best that they put
on their thinking caps and find solutions to resolve this brewing
crisis. Renegotiation of power contracts is something that has been
successfully done in South Korea, and lately, in the United States.
There's no reason why it couldn't be done here.
Some IPPs in
the country have already recovered their investment and have earned
more than enough. Some are looking at doing business in the country
for many more years. Changing terms of doing business should not
necessarily mean losing money. Businesses, especially those that
look at the longer-term horizon, cannot ignore the environment where
they operate. It is perhaps time to hear their customers' cries.
Before I end
this column, Meralco customers may find it interesting to know that
Napocor is not the only entity with IPP contracts. Other big distributors
including Meralco can also get their power directly from IPPs.
From hearings
at the Lower House, at least two-thirds of the P3.22-per-kwh purchase
power adjustment charge in its recent monthly bill is directly from
its own IPPs; the effect of Napocor's IPP contracts represent only
a third.
For the sake
of transparency, it is only fitting that each item in the billing
statement be clearly described. The paying public deserves to know.
TOP
|